Illawarra Water Security project

Illawarra Water Security project

About the project

Since February 2019, when total dam storage levels declined to 60 percent, the Illawarra Water Security project has been investigating options to access 67 gigalitres (GL) of deep water stored in Lake Avon. Accessing this deep water will extend the available water supply by up to two years for the Illawarra Region and will increase long term yield by 5 GL (5 billion litres) per year.

Due to recent rainfall events in February 2020 and the resulting increase in storage levels of Avon Dam, the construction phase of the project is on hold and is being reassessed. Detailed planning is continuing as planned.

The project involves a deep water pumping station at Avon Dam and a pipeline to transfer water to the existing Illawarra Water Filtration Plant. WaterNSW, as the owner and operator of Avon Dam, will continue to inform stakeholders about the project as the planning phase continues.

The NSW Government’s Metropolitan Water Plan 2017 requires WaterNSW to investigate drought supply options when Greater Sydney total dam storage levels reach 60 percent.

Accessing the deep water in Avon Dam was first considered during the Millennium drought and deep water access projects have already been completed at Warragamba and Nepean dams.

Project timeline

  • May 2019 – Preliminary planning started
  • August 2019 – Early investigation, preliminary design, stakeholder engagement commenced
  • October 2019 to late 2020 – Detailed planning phase
  • Plans for construction on hold and being reassessed

皇冠代理For more information on the planning process, visit .

Project Fact Sheet

For more information, see our project fact sheet (PDF, 350.61 KB).

Frequently Asked Questions

Avon Dam is located about 100 kilometres south of Sydney and is the largest of the four dams constructed to collect water from the Illawarra Plateau. Created by damming the Avon River and completed in 1927, Avon Dam is the main water supply source for the Illawarra region. It is one of the 10 major dams in the Sydney Metropolitan Water Supply Scheme. It is the second largest reservoir after Warragamba Dam.

皇冠代理Deep water is water which is currently inaccessible to the water supply system. Usually, it is below the lowest outlet point in a dam from where water can be extracted, or below the level where gravity can draw the water from the dam.

皇冠代理Yes. In the Millennium Drought, the Metropolitan Water Plan identified deep water access as a drought response measure for the Sydney basin. Deep water pumping stations were installed at Nepean and Warragamba Dams to increase accessible water supply.

The project involves a deep water pumping station at Avon Dam and a pipeline to transfer water to the existing Illawarra Water Filtration Plant.

This will make available water which currently cannot be accessed thus increasing the volume of accessible water. This will improve water security and extend the water supply for the Illawarra region.

The project once constructed will provide access up to an additional two years of water supply for the Illawarra region.

皇冠代理Thorough investigation and assessment processes will be undertaken to ensure the project has minimal impacts to the environment. On-site environmental investigations began in September 2019.

皇冠代理Avon Dam is remotely located and surrounded by land managed by WaterNSW and National Parks and Wildlife Services.

Privately owned properties will not be impacted by the project.

皇冠代理The WaterNSW team will liaise closely with stakeholders as the project develops.

Avon Dam is a heritage structure and is protected under the Heritage Act 1977. This project will be planned to minimise construction and operational impacts to the dam wall and heritage structures.

皇冠代理Water quality tests show the quality of the water in deep storage is good. Water in Avon Dam is naturally mixed and aerated. These natural and mechanical processes will aim to keep the quality of water in the dam consistent from top to bottom.

皇冠代理Water quality at this level will be monitored to ensure it meets the water filtration plant requirements.

WaterNSW is committed to providing stakeholders with clear, concise and timely information about the Illawarra Water Security Project and welcomes feedback.

If you would like any more information on this project, please contact WaterNSW.

This project is currently in the planning phase and a business case has been submitted to Infrastructure NSW.

Due to recent rainfall events in February 2020 and the resulting increase in storage levels of Avon Dam, the construction phase of the project is on hold and is being reassessed. Detailed planning will continue as planned.

Contact us

If you would like any more information about this project please contact WaterNSW.