Blue Mountains assets upgrade

Blue Mountains assets upgrade

About the project

WaterNSW is continuing to deliver the Blue Mountains Asset Upgrade program to refurbish and restore various assets across dams, weirs, regulators and water supply infrastructure to improve water delivery to our customers.

电竞大师iosInitiated in 2017, the program aims to improve access conditions, facilitate efficient water delivery and ensure that infrastructure continues to meet current operation and safety standards, environmental and heritage requirements.

The second program of work is underway and construction is planned to start in October 2019 and due for completion in Mid 2020.

电竞大师iosWorks will be completed in stages as sites are prioritised based on current condition and with the more critical assets being scheduled first. Remaining sites will be assessed and scheduled in future work programs.

电竞大师iosAsset locations in the Blue Mountains to be upgraded includes:

  • Upper Cascades dam and pumping station
  • Middle Cascade dam and pumping station
  • Lower Cascades dam and pumping station
  • Whipcord Creek Weir
  • Lake Medlow dam
  • Greaves Creek dam and pumping station
  • Narrow Neck pumping station

Benefits

  • This work will ensure WaterNSW continues to maintain water supply infrastructure as well as meet current operation and safety requirements.
  • During construction, there will be additional contractors staying in the Blue Mountains which will benefit Katoomba and surrounding areas.

During the upgrade

During construction, there will be some increase in personnel, vehicle movements, noise and dust near the sites. Prior to work starting landowners near our work sites will be notified.

At relevant sites, water flows will be interrupted during stages of the project to allow access to refurbish infrastructure. Affected customers will be notified prior to the outage.

Project schedule

  • October 2019 – upgrade work to start
  • Mid 2020 – upgrade work scheduled to finish

Contact details

For more information about the upgrades or to enquire about any of the project activities contact us电竞大师ios or call 1300 662 077.

Project Manager: Janaka Weeraratne